← ALL PROJECTS
SIDERURGIA — GUAYANA//Puerto Ordaz, Bolívar//2022
25 sinter cars, from drawing to port
ACTUAL PROJECT PHOTO
A sinter plant doesn't wait. RELANSA, with its procurement ally NLM Corp, managed the design, fabrication and supply of 25 complete sinter cars for a Guayana steel mill.
25
SINTER CARS
TECHNOLOGY BY
RELANSA · NLM Corp
Steel & Aluminum
TECHNICAL DATAREF-2022-19
SCOPEDISEÑO + FABRICACIÓN + SUMINISTRO
QUANTITY25 SINTER CARS
EXECUTION2022
CHANNELRELANSA + NLM CORP
REPRESENTATIVERELANSA S.A.
01
THE CHALLENGE
Replace the sinter car fleet of an operating steel mill, with engineering true to the original design and certified fabrication abroad.
02
THE SOLUTION
Design, fabrication and testing of 25 sinter cars with European manufacturers, managed end-to-end by the RELANSA–NLM channel: engineering, factory QA and logistics to a Venezuelan port.
03
THE IMPACT
Equipment fabricated, tested and delivered. The sinter line recovers design capacity with new — not repaired — components.